The Professional Scrum Product Owner™ certification is a product of Scrum.org (PSPO I). The open assessments on their website are quite good – just the number of questions is small. Practising with additional reliable tests before sitting for the real exam is highly recommended. The PSPO I Exam Simulation is an ideal tool for this. All Scrum questions reflect the latest Scrum Guide (2020).
A pool of more than 100 Scrum test questions!
This PSPO I exam simulation test works from a pool of questions. A product owner must have a strong knowledge of the Scrum Guide with special attention to the responsibilities of the Product Owner. It is not enough to learn the Scrum Guide, one must understand the context of Scrum: metrics, agile techniques, and practices.
Professional Scrum Product Owner™ I Practice Test
The test is free. No sign-up is required. No re-take limit applies.
The correct answers are explained at the end of the test.
Recommended reading: apart from the Scrum Guide and the Evidence-Based Management Guide, the Product Owner Study Guide and Scrum: The Guide Explained.
Disclaimer: This is a third-party practice test, created independently from Scrum.org the provider of Professional Scrum Product Owner™ certification. The questions are different from real exam questions, however, similar in nature, difficulty and number.
Fantastique ! Merci beaucoup
Lovely – scenario based questions! Thought provoking. Glad I found this link.
I would challenge the answer to this question: What is the size of the Scrum Team?
> Minimum 3 and maximum 10 members
> Typically 10 or less members (this should be correct as per new Scrum Guide)
> Ideally 3-9 members (but you marked this as correct)
> 7 plus/minus 2 members
Should be “Typically 10 or less members”, agreed.
agree
Team size answer has been fixed. Fortunately, the answer page was correct.
Thank you! here is another one, if somebody wants to keep on practicing https://internet80.com/pspo-i-exam-simulator-1/
Question 53 has two answers that are basically identical, but you have only one of them allowed as correct:
“This is at most a four-hour meeting for one-month Sprints. For smaller teams, the event is usually shorter.”
vs
“The Sprint Review is a time-boxed event which should not be longer than 4 hours for a one-month Sprint. The time-box does not depend on team size.”
Both of these say the same thing: no longer than 4 hours for a 1-month sprint, timebox flexes based on team size.
Hi Matt,
“For smaller teams, the event is usually shorter” expresses the opposite of “The time-box does not depend on team size“. The latter is correct.
Thank you. It is by far the best test, I refer to the explanations based on the new guide and also to the complexity and realness.
Thank you. By far the best test and explanation.
The first three questions are about Scrum Master duties. I thought this was a PSPO I test?
Hi there, the questions are randomly picked from a pool, in a random order, and some of the PSPO questions should ask about the roles.
Question 41: Refinement usually consumes no more than 10% of the capacity of the team. Which Sprint is it focusing on?
Your Answer says: Upcoming Sprint.
Right Answer should be Current Sprint because Scrum Guide 2020 says:
Through discussion with the Product Owner, the Developers select items from the Product Backlog to include in the current Sprint. The Scrum Team may refine these items during this process, which increases understanding and confidence(this is under Sprint Planning).
Hello There, the correct answer is the upcoming Sprint, please consider:
“Product Backlog items that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event. They usually acquire this degree of transparency after refining activities.”
This statement implies most of the refinement of a product backlog item happens before the item is selected into a Sprint, even though this is not to say no further refinement can take place as we learn more about the problems.
Wonderful learning website!
I would challenge question 28 though:
“The “cone of uncertainty” is one of the notions frequently used in agile thinking. What does it express?”
given answer: “It illustrates that the further we look into the future the less certain our forecast will be.”
so far my understanding is one of the opposite. The longer your project, the more variables are known ergo the more certain we are to deliver results. What´s the correct answer?
You might be right that more variables are known for big projects, however, more variables with the same margin of error add up to a bigger margin of error. In addition, not all uncertainties are linked to the product itself but to the changing environment. According to different statistics, long and complex projects are more likely to fail, even in infrastructure. Consider these examples:
The time elapsed between the decision to start the project – something that was probably underpinned by massive planning and calculations – changed the circumstances, rendering the goal obsolete, unattainable or undesirable.
DiD you change the right answers recently?
No change in 2022.
Scenario: your team uses user stories to define Product Backlog Items. Who is responsible for writing user stories?
a) The Business analyst
b) Scrum leaves it up to the self-organizing team
c) The Product Owner
d) The Development team
The answer feedback says the right answer is B, that “In Scrum, there is no hard rule about who should write user stories.”
Yes, but the Scrum Guide says:
“The Product Owner is also accountable for effective Product Backlog management, which includes:
CREATING and clearly communicating Product Backlog items;”
Thus, isn’t letter C the most appropriate?
Good observation. However, the Scrum Guide also states: “The Product Owner may do the above work or may delegate the responsibility to others.” Also, a user story is a freely chosen format for describing product backlog items, which is the level of detail not covered by the Scrum Guide.
Pingback: make tadalafil
top, je suis tombée par hasard j’ai de la change le format est top, top